S T A T E O F N E W Y O R K
________________________________________________________________________
11115
I N A S S E M B L Y
November 6, 2020
___________
Introduced by COMMITTEE ON RULES -- (at request of M. of A. Paulin) --
read once and referred to the Committee on Corporations, Authorities
and Commissions
AN ACT to amend the public service law, in relation to storm hardening
and system resiliency plans
THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM-
BLY, DO ENACT AS FOLLOWS:
Section 1. Legislative findings. 1. The Legislature hereby finds and
declares that, due to the rise in storm intensity, dedicated storm hard-
ening programs need to be developed and implemented throughout New York
State to reduce damage and costs from future weather events. Storm hard-
ening is the process of constructing new, or upgrading old, infrastruc-
ture to increase resiliency and overall reliability during weather
events. In 2018, Winter Storm Riley and Winter Storm Quinn greatly
impacted New York's electric distribution system with nearly 500,000
customers losing power. In August 2020, Tropical Storm Isaias brought
high winds, downed trees and widespread power outages to much of the
state; hundreds of thousands of customers in Long Island, New York City,
Westchester and Rockland counties experienced extensive power outages,
some lasting for more than a week. Legislative hearings following these
storms made it clear that storm hardening efforts are needed to mitigate
some of the impacts to the distribution infrastructure and customers.
2. An investigation by the Department of Public Service recommended
New York's major electrical utilities create and implement storm harden-
ing and system resiliency plans by July 2019. Plans should detail future
storm hardening measures and include a budget, timeline, and major
performance benchmarks.
(a) It is in the state's interest to strengthen electric utility
infrastructure to withstand extreme weather conditions by promoting the
hardening of electrical transmission and distribution facilities, the
undergrounding of certain electrical distribution lines, and vegetation
management;
(b) Protecting and strengthening transmission and distribution elec-
trical utility infrastructure from extreme weather conditions can effec-
EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
[ ] is old law to be omitted.
LBD17527-03-0
A. 11115 2
tively reduce restoration costs and outage times to customers and
improve overall service reliability for customers;
(c) It is in the state's interest for each utility to mitigate resto-
ration costs and outage times to utility customers when developing tran-
smission and distribution storm protection plans; and
(d) All customers benefit from the reduced costs of storm restoration.
§ 2. Section 66 of the public service law is amended by adding a new
subdivision 29 to read as follows:
29. (A) EACH ELECTRIC CORPORATION SUBJECT TO SECTION TWENTY-FIVE-A OF
THIS CHAPTER SHALL, PURSUANT TO REGULATION BY THE COMMISSION, SUBMIT A
STORM HARDENING AND SYSTEM RESILIENCY PLAN THAT COVERS THE IMMEDIATE
TEN-YEAR PERIOD TO THE COMMISSION FOR REVIEW AND APPROVAL. EACH PLAN
SHALL EXPLAIN THE SYSTEMATIC APPROACH THE CORPORATION WILL FOLLOW TO
ACHIEVE THE OBJECTIVES OF REDUCING RESTORATION COSTS AND OUTAGE TIMES
ASSOCIATED WITH EXTREME WEATHER EVENTS AND ENHANCING RELIABILITY, AS
WELL AS SUCH OTHER ADDITIONAL OBJECTIVES THE COMMISSION MAY REQUIRE
CONSISTENT WITH ENSURING INCREASED RESILIENCY OF UTILITY INFRASTRUCTURE
AND OVERALL RELIABILITY DURING EXTREME WEATHER EVENTS. THE COMMISSION
SHALL ADOPT RULES TO SPECIFY THE ELEMENTS THAT MUST BE INCLUDED IN A
CORPORATION'S FILING FOR REVIEW OF STORM HARDENING AND SYSTEM RESILIENCY
PLANS.
(B) IN ITS REVIEW OF EACH STORM HARDENING AND SYSTEM RESILIENCY PLAN
FILED PURSUANT TO THIS SUBDIVISION, THE COMMISSION SHALL, AT MINIMUM,
CONSIDER:
(I) THE EXTENT TO WHICH THE PLAN IS EXPECTED TO REDUCE RESTORATION
COSTS AND OUTAGE TIMES ASSOCIATED WITH EXTREME WEATHER EVENTS AND
ENHANCE RELIABILITY, INCLUDING WHETHER THE PLAN PRIORITIZES AREAS OF
LOWER RELIABILITY PERFORMANCE;
(II) THE EXTENT TO WHICH STORM PROTECTION AND HARDENING OF TRANS-
MISSION AND DISTRIBUTION INFRASTRUCTURE IS FEASIBLE, REASONABLE, OR
PRACTICAL IN CERTAIN AREAS OF THE CORPORATION'S SERVICE TERRITORY,
INCLUDING, BUT NOT LIMITED TO, COASTAL AREAS, FLOOD ZONES, AND RURAL
AREAS;
(III) THE ESTIMATED COSTS AND BENEFITS TO THE CORPORATION AND ITS
CUSTOMERS OF MAKING THE IMPROVEMENTS PROPOSED IN THE PLAN;
(IV) THE TIMELINE FOR IMPLEMENTATION OF THE PLAN;
(V) WHETHER THE PLAN INCLUDES MAJOR PERFORMANCE BENCHMARKS THAT MEAS-
URE THE EFFECTIVENESS OF THE IMPLEMENTATION OF THE PLAN;
(VI) THE ESTIMATED ANNUAL RATE IMPACT RESULTING FROM IMPLEMENTATION OF
THE PLAN DURING THE FIRST TWO YEARS ADDRESSED IN THE PLAN; AND
(VII) THE EXTENT TO WHICH THE PLAN CONSIDERS A MULTI-PRONGED STRATEGY
APPROPRIATELY TAILORED TO REDUCING RESTORATION COSTS AND OUTAGE TIMES
AND ENHANCING INFRASTRUCTURE RELIABILITY, INCLUDING, BUT NOT LIMITED TO,
VEGETATION MANAGEMENT, IMPROVEMENTS TO SYSTEM MANAGEMENT PRACTICES,
UNDERGROUNDING OF DISTRIBUTION AND TRANSMISSION LINES, REPLACEMENT OF
OBSOLETE CABLES, WIRES AND POLES, AUTOMATION AND CIRCUIT RECONFIGURA-
TION, AND FORTIFYING CRITICAL STEAM PRODUCTION FACILITIES.
(C) NO LATER THAN ELEVEN MONTHS AFTER A CORPORATION FILES A STORM
HARDENING AND SYSTEM RESILIENCY PLAN THAT CONTAINS ALL OF THE ELEMENTS
REQUIRED BY THIS SUBDIVISION AND THE COMMISSION, THE COMMISSION SHALL
DETERMINE WHETHER IT IS IN THE PUBLIC INTEREST TO APPROVE, MODIFY, OR
DENY THE PLAN.
(D) AT LEAST EVERY THREE YEARS AFTER APPROVAL OF A CORPORATION'S STORM
HARDENING AND SYSTEM RESILIENCY PLAN, THE CORPORATION MUST FILE FOR
COMMISSION REVIEW AN UPDATED STORM HARDENING AND SYSTEM RESILIENCY PLAN
THAT ADDRESSES EACH ELEMENT SPECIFIED BY COMMISSION REGULATION. THE
A. 11115 3
COMMISSION SHALL APPROVE, MODIFY, OR DENY EACH UPDATED PLAN PURSUANT TO
THE CRITERIA USED TO REVIEW THE INITIAL PLAN.
(E) THE COMMISSION SHALL CONDUCT AN ANNUAL PROCEEDING TO DETERMINE THE
CORPORATION'S STORM HARDENING AND SYSTEM RESILIENCY PLAN COSTS AND ALLOW
THE CORPORATION TO RECOVER SUCH COSTS THROUGH A CHARGE SEPARATE AND
APART FROM ITS BASE RATES, TO BE REFERRED TO AS THE STORM HARDENING PLAN
COST RECOVERY CLAUSE. IF THE COMMISSION DETERMINES THAT SUCH COSTS ARE
JUST AND REASONABLE, AND WERE PRUDENTLY INCURRED, THOSE COSTS WILL NOT
BE SUBJECT TO DISALLOWANCE OR FURTHER REASONABLENESS OR PRUDENCE REVIEW
EXCEPT FOR FRAUD, PERJURY, OR INTENTIONAL WITHHOLDING OF KEY INFORMATION
BY THE CORPORATION. THE ANNUAL STORM HARDENING PLAN COSTS MAY NOT
INCLUDE COSTS RECOVERED THROUGH THE CORPORATION'S BASE RATES AND MUST BE
ALLOCATED TO CUSTOMER CLASSES PURSUANT TO THE RATE DESIGN MOST RECENTLY
APPROVED BY THE COMMISSION. IF A CAPITAL EXPENDITURE IS RECOVERABLE AS
A STORM HARDENING PLAN COST, THE CORPORATION MAY RECOVER THE ANNUAL
DEPRECIATION ON THE COST, CALCULATED AT THE CORPORATION'S CURRENT
APPROVED DEPRECIATION RATES, AND A RETURN ON THE UNDEPRECIATED BALANCE
OF THE COSTS CALCULATED AT THE CORPORATION'S WEIGHTED AVERAGE COST OF
CAPITAL USING THE LAST APPROVED RETURN ON EQUITY.
(F) EACH CORPORATION SHALL FILE WITH THE COUNTY EXECUTIVE OR THE CHIEF
ELECTED OFFICIAL OF A COUNTY FOR EACH COUNTY WITHIN ITS SERVICE TERRITO-
RY THE MOST RECENT APPROVED COPY OF THE STORM HARDENING AND SYSTEM RESI-
LIENCY PLAN REQUIRED PURSUANT TO THIS SUBDIVISION. FOR THE PURPOSES OF
AN ELECTRIC CORPORATION OPERATING WITHIN THE CITY OF NEW YORK, SUCH
CORPORATION SHALL FILE THE MOST RECENT APPROVED STORM HARDENING AND
SYSTEM RESILIENCY PLAN WITH BOTH THE MAYOR'S OFFICE AND EMERGENCY
MANAGEMENT OFFICE OF THE CITY OF NEW YORK.
(G) THE COMMISSION SHALL PROVIDE ACCESS TO SUCH STORM HARDENING AND
SYSTEM RESILIENCY PLANS PURSUANT TO ARTICLE SIX OF THE PUBLIC OFFICERS
LAW.
(H) BEGINNING DECEMBER FIRST OF THE YEAR AFTER THE FIRST FULL YEAR OF
IMPLEMENTATION OF A STORM HARDENING AND SYSTEM RESILIENCY PLAN AND ANNU-
ALLY THEREAFTER, THE COMMISSION SHALL SUBMIT TO THE GOVERNOR AND THE
LEGISLATURE A REPORT ON THE STATUS OF EACH CORPORATION'S STORM
PROTECTION ACTIVITIES. THE REPORT SHALL INCLUDE, BUT IS NOT LIMITED TO,
IDENTIFICATION OF ALL STORM PROTECTION AND RESILIENCY ACTIVITIES
COMPLETED OR PLANNED FOR COMPLETION, THE ACTUAL COSTS AND RATE IMPACTS
ASSOCIATED WITH COMPLETED ACTIVITIES AS COMPARED TO THE ESTIMATED COSTS
AND RATE IMPACTS FOR THOSE ACTIVITIES, AND THE ESTIMATED COSTS AND RATE
IMPACTS ASSOCIATED WITH ACTIVITIES PLANNED FOR COMPLETION.
(I) THE COMMISSION SHALL PROMULGATE ANY NECESSARY RULES AND REGU-
LATIONS TO IMPLEMENT AND ADMINISTER THE PROVISIONS OF THIS SUBDIVISION.
§ 3. This act shall take effect on the one hundred eightieth day after
it shall have become a law. Effective immediately, the promulgation of
any rules or regulations by the Public Service Commission necessary for
the implementation of this act on its effective date are authorized to
be made and completed on or before such effective date.