SECTION 489-HHH
Extension of time for completion
Real Property Tax (RPT) CHAPTER 50-A, ARTICLE 4, TITLE 2-C
§ 489-hhh. Extension of time for completion. Where an applicant has
received a certificate of eligibility but has not completed or will not
be able to complete the construction or reconstruction work within
thirty-six months, the board shall, upon application, extend to
forty-eight months, from the time of issuance of such certificate, the
time for completion of the construction or reconstruction work; provided
the applicant has completed not less than two-thirds of the work as
specified in the certified plans previously filed with the application
at the time of such application for extension.
received a certificate of eligibility but has not completed or will not
be able to complete the construction or reconstruction work within
thirty-six months, the board shall, upon application, extend to
forty-eight months, from the time of issuance of such certificate, the
time for completion of the construction or reconstruction work; provided
the applicant has completed not less than two-thirds of the work as
specified in the certified plans previously filed with the application
at the time of such application for extension.